Streets Update
Contractors have begun milling East Main Street as of today, August 20th.
With the dryer weather, Michigan Paving is planning on starting top coating of Forest, Eastlawn, Westlawn, Fulton, etc in roughly the same order that they have done the base paving coats.
As of today, Michigan Paving plans on Milling West Main, Church, Parker and Mill streets on Tuesday, August 27th.
During the milling work, all vehicles will need to be moved off the streets. The milling will be done during daylight hours, and access to the village hall and businesses will be maintained. Michigan Paving will try to get the base course paved the same day, but logistical and scheduling factors may permit otherwise. Regardless, they will try to make as quick of a turnaround as possible.